Railway construction in Walchwil 1895–1897
More actions

Railway construction in Walchwil lasted from summer 1895 until the opening of the Zug–Goldau line on 30 May 1897. The client was the Gotthard Railway Company (Gotthardbahn-Gesellschaft). On Walchwil territory, landslides made construction difficult: at St. Adrian an embankment had to be replaced by an iron bridge. For the station and the later history of the line, see Walchwil railway station and the Zug–Arth-Goldau line.
Planning
The Federal Council approved the section of the line from the Lothenbach to the Kienbach in January 1892.[1] Its decision, however, called for several significant changes, so the plans were put on public display in Walchwil again in early 1892.[2] On 29 August 1893 the Federal Council approved the revised construction project for the territory of the municipality of Walchwil.[3][4]
Leo Hürlimann recalled in 1962 that opinions in Arth and Walchwil had differed widely on whether the line should take a lower or a higher route. According to him, the 1893 decision went in favour of the higher route and thus in Walchwil's favour, and the people of Walchwil then celebrated the coming of the railway with a Fasnacht (carnival) procession.[5] No contemporary evidence for this has been found.
Contracts and start of construction
Construction had still not begun in 1894. The Gotthard Railway's annual report for that year states: “On the Zug-Goldau line, construction could not yet begin.”[6] The contract for the line's iron bridges was awarded to the Società nazionale delle Officine di Savigliano.[6] In February 1895 complaints were made in the cantonal parliament (Kantonsrat) about the delays to the works.[7]
In April 1895 the first sod was turned at the Dreiangel in the town of Zug.[7] Work on the first contract lot began on 25 April 1895.[8] The Gotthard Railway's management put the section through Walchwil out to tender on 23 June 1895: from the Friedbach to the end of the bridge over the Rufibach. The tender divided the section into two lots. The first ran as far as the bridge over the Lothenbach. The second, from the Lothenbach to the Rufibach, was 3,424 m long and involved around 173,000 m³ of earth and rock excavation, 22,600 m³ of masonry and three tunnels with a combined length of about 170 m.[9] Construction in Walchwil therefore began in summer 1895 at the earliest.
The Zug–Goldau line was divided into five contract lots. The second lot, from the Friedbach to the Lothenbach, was built by the engineer Konrad Hitz of Zurich. The third lot, from the Lothenbach to the Rufibach with three tunnels, and the fourth, from the Rufibach to the Kienbach, were taken on by Giuseppe Catella and Domenico Dagossa of Turin.[8] For Walchwil, Hürlimann names the “Gebrüder Catella von Turin” (Catella brothers of Turin) and recalls construction starting in autumn 1894.[5] Neither matches the contemporary sources.
Workers
It was hard to find enough workers. Most of them were Italians.[8] In June 1895 the town of Zug approved funds for a fourth policeman “for the duration of the railway construction”.[7]
According to Hürlimann, close to 1,000 Italians were working in Walchwil at the same time along the whole length of the works. He wrote that every empty room in the village was taken and that four large barracks were built as well: by the station, by the Rust butcher's shop on the lakeshore, behind the Gasthaus Engel and by the Lothenbach. The contractors' office, he said, was in the Rust butcher's shop building, and the work was done almost without machines, using pickaxes, shovels, wheelbarrows, tip wagons and hand drills.[5] The number of workers is not documented in contemporary sources.
Landslides and the bridge at St. Adrian
1896 brought a wet summer, with a “worrying period of rainfall” from mid-July to the end of September. On the Zug–Goldau line, “repeated landslides” caused the Gotthard Railway Company and the cantonal government “grave concern”.[10] In January 1897 the Gotthard Railway decided to replace the embankment at St. Adrian with a bridge.[10]
Hürlimann describes this landslide in more detail. According to him, the spoil from the St. Adrian tunnel and from the southern part of the Rossplatten tunnel was intended for a large embankment in the “Reiste”, where the iron bridge stands today. In the wet summer of 1896, he wrote, the ground between the embankment and the lake began to slide into the lake, together with the embankment, over a height of about 150 m and a width of 200 m. Heavy carts, he added, could now use the cantonal road only at their own risk, and the ground came to rest only once the water above it had been drained off. The embankment, he said, was taken away by tip wagons about 400 m towards the “Bändli” on Schwyz territory; the foundations of the iron bridge went down to the bedrock, 96 feet deep on the north side. Until the bridge was finished, he wrote, trains ran over a temporary wooden bridge. As a boy, Hürlimann saw engine drivers refuse to take heavy locomotives over the wooden bridge; after that only the lightest locomotives crossed it.[5]
It is documented that the iron bridge at St. Adrian was finished only after the line had opened: during an excursion in October 1897 it had “now been completed”, and the difficulties caused by the “unreliable subsoil” had been “almost overcome”.[11] Today the masonry St. Adrian viaduct stands there, adjoined by a steel truss bridge (see Bridges in Walchwil and St. Adrian).
Further difficulties
During the same excursion, a “high embankment” north of Walchwil station was still being rebuilt.[11] The Railway Department's report for 1897 mentions “repeated subsidence of embankments near Walchwil”.[12]
Hürlimann names other places where water in the ground disrupted the work. As he remembered it, farmers had warned the builders from the outset to drain the water first:[5]
- At the northern end of the Rossplatten tunnel, he wrote, the tipped rock slid into the lake in autumn 1895; after that the water was collected and a retaining wall was built.
- In the Obersecki cutting, the almost finished wall on the uphill side was, according to him, found lying on the trackbed one morning.
- At Eichhof a tunnel is said to have been planned and already excavated, and then to have collapsed. According to Hürlimann, the material, together with a landslip from the Gruob (Kirchmatt), was taken to the station area by a small steam locomotive, which is why the station area ended up much larger than planned.
- At the “Damm” (embankment), the retaining wall reportedly gave way. There too, he wrote, trains ran over a temporary wooden bridge for several months.
In all, according to Hürlimann, construction on Walchwil territory cost around one million francs more than estimated.[5] These statements have not so far been confirmed in contemporary sources.
Station and roads
Opening
Effects on the village
On 28 November 1897 Walchwil complained that the catch of Zug char (Rötel) had declined: the railway, it said, had dumped material on the Rötel grounds laid with clean gravel.[10] On the Rötel, see Zug char (Rötel) and fishing in Walchwil.
On 4 February 1900 the municipality of Walchwil approved an agreement with the Gotthard Railway, under which all of the municipality's claims relating to the road realignments in the village were settled with a payment of 6,700 francs.[15]
The sources
The most detailed account of the construction in Walchwil comes from Leo Hürlimann (1885–1970). He was a boy of nine to eleven while the line was being built and wrote down his memories some 65 years later. Where his statements could be checked, they are correct in essence (the 1893 decision, the landslides of 1896, an iron bridge instead of an embankment at St. Adrian). On dates and names he sometimes departs from the sources (construction starting in 1894, “Gebrüder Catella”).
Open questions
- Annual reports 1895–1897: The Gotthard Railway's annual reports for these years were not found online. They could document landslides, cost overruns and site management. Possible sources: SBB Historic archive, Zug State Archives.
- Site management: Hürlimann names an “Ober-Ingenieur Koller” (chief engineer). The annual reports for 1891–1894 name an engineer Koller from Bern as a substitute member of the management, not as chief engineer. Whether he is the man meant remains open. On the 1897 excursion the party was led by Director Dietler and section engineer Drossel.[11]
- Higher or lower route: How the 1892/93 variants differed, and whether Arth wanted a different route, is not documented.
- Eichhof tunnel: A planned tunnel at Eichhof is mentioned only by Hürlimann.
- Accidents: Nothing was found on whether any workers met with accidents during construction in Walchwil.
See also
References
- ↑ Zwanzigster Geschäftsbericht der Direktion und des Verwaltungsrates der Gotthardbahn (year 1891). Luzern 1892, p. 17, digitale-sammlungen.de, accessed 15 November 2026.
- ↑ Einundzwanzigster Geschäftsbericht der Direktion und des Verwaltungsrates der Gotthardbahn (year 1892). Luzern 1893, p. 14, digitale-sammlungen.de, accessed 15 November 2026.
- ↑ Zweiundzwanzigster Geschäftsbericht der Direktion und des Verwaltungsrates der Gotthardbahn (year 1893). Luzern 1894, p. 19, digitale-sammlungen.de, accessed 15 November 2026.
- ↑ Chronik des Kantons Zug, entry for 29 August 1893. In: Zuger Neujahrsblatt 1897, p. VI, zentralgut.ch, accessed 15 November 2026.
- ↑ 5,0 5,1 5,2 5,3 5,4 5,5 Leo Hürlimann: In Walchwil dem zugerischen Nizza. Zug: Offizin Zürcher, n.d. (preface 1962), pp. 100–105.
- ↑ 6,0 6,1 Dreiundzwanzigster Geschäftsbericht der Direktion und des Verwaltungsrates der Gotthardbahn (year 1894). Luzern 1895, p. 18, digitale-sammlungen.de, accessed 15 November 2026.
- ↑ 7,0 7,1 7,2 Chronik des Kantons Zug, entries for 28 February, April, 24 June and 4 September 1895. In: Zuger Neujahrsblatt 1898, zentralgut.ch, accessed 15 November 2026.
- ↑ 8,0 8,1 8,2 Hans Koch: Vom zugerischen Eisenbahnwesen. In: Zuger Neujahrsblatt 1974, pp. 105–119, here p. 115, zentralgut.ch, accessed 4 November 2026.
- ↑ Gotthardbahn. Zug-Goldau. Ausschreibung von Bauarbeiten (Luzern, 23. Juni 1895). In: Schweizerische Bauzeitung 25 (1895), No. 26 of 29 June 1895, advertisement section, e-periodica.ch, accessed 15 November 2026.
- ↑ 10,0 10,1 10,2 10,3 10,4 Chronik des Kantons Zug für die Jahre 1896 und 1897, pp. V–IX. In: Zuger Neujahrsblatt 1899, zentralgut.ch, accessed 15 November 2026.
- ↑ 11,0 11,1 11,2 Gesellschaft ehemaliger Polytechniker: Exkursion vom 24. Oktober 1897. In: Schweizerische Bauzeitung 30 (1897), No. 19 of 6 November 1897, pp. 147–148, e-periodica.ch, accessed 15 November 2026.
- ↑ Schweizerische Bauzeitung 31 (1898), p. 127 (Bericht über die schweizerischen Eisenbahnen im Jahr 1897), e-periodica.ch, accessed 4 November 2026.
- ↑ Ausschreibung Aufnahmegebäude Walchwil. In: Schweizerische Bauzeitung 26 (1895), No. 17 of 26 October 1895, advertisement section, e-periodica.ch, accessed 15 November 2026.
- ↑ Submissions-Anzeiger. In: Schweizerische Bauzeitung 28 (1896), No. 19 of 7 November 1896, e-periodica.ch, accessed 15 November 2026.
- ↑ Chronik des Kantons Zug für das Jahr 1900, entry for 4 February 1900. In: Zuger Neujahrsblatt 1902, zentralgut.ch, accessed 15 November 2026.